Construction Phase - The construction phase is the period from the groundbreaking ceremony to the completion and acceptance of a building. It encompasses all stages of construction-from excavation and structural work to interior finishing and final acceptance. The construction phase forms the core of the construction project and follows the planning and permitting phase.
The construction phase of a residential building is divided into several sequential phases:
| Construction Phase | Typical Duration | Key Milestones |
|---|---|---|
| Earthwork & Foundations | 4-8 weeks | Excavation, floor slab/foundations, waterproofing |
| Structural Work | 3-5 months | Load-bearing walls, ceilings, roof truss, topping-out ceremony |
| Roof & Facade | 6-10 weeks | Roofing, windows, facade insulation |
| Building Services | 8-12 weeks | Electrical, plumbing, heating, ventilation |
| Interior Finishing | 3-5 months | Plaster, screed, tiles, flooring, doors, painting |
| Exterior Work | 4-8 weeks | Driveway, patio, landscaping |
| Total | 12-18 months | Completion and final inspection |
Earthwork and Foundations: Excavation of the building pit, foundation or floor slab, drainage, and waterproofing-for buildings with basements, this also includes basement construction. This phase is highly weather-dependent and often takes longer than planned.
Shell Construction: Erection of load-bearing walls, ceilings, and the roof structure. The completion of the shell is traditionally celebrated with a topping-out ceremony-a milestone that brings joy to both the homeowner and the tradespeople alike and marks an important date for the first progress payment.
Building Services: Installation of electrical, plumbing, and heating systems, as well as ventilation and photovoltaic systems if applicable. Coordinating the building services trades is often a bottleneck in the construction schedule-especially when different subcontractors are waiting for one another.
Interior finishing: Plastering and screed work, drywall installation, tiling, flooring, painting, and door installation. This is the most visible phase for the client, during which the character of the building takes shape.
The construction phase is closely linked to the payment schedule. In property development contracts, the payment schedule is governed by the Real Estate Brokerage and Property Development Ordinance (MaBV): Progress payments may only be called for once construction progress has been achieved and against appropriate security. In general contractor contracts, § 650m BGB stipulates that progress payments must correspond to the value of the work completed and that the contractor must provide a 5% completion guarantee. We recommend linking the payment schedule to performance milestones-not calendar dates-to avoid payments without corresponding consideration.
The construction phase entails various risks that affect costs and the schedule:
We recommend that building owners in the Nuremberg metropolitan region have the construction phase monitored by an independent construction supervisor or construction consultant. Quality control throughout the construction process-for example, by an expert from TÜV Süd, DEKRA, or an architectural firm-typically costs 3,000-6,000 euros for a single-family home and uncovers hidden defects before they become costly. The inspection usually includes visits during critical phases (waterproofing, shell construction, roofing, building services) as well as a final acceptance inspection.
In Nuremberg and the metropolitan region, tradespeople are in particularly short supply-leading companies in the electrical, plumbing, and heating sectors are often booked up 6-12 months in advance. Also, plan for a buffer of at least 10-15% in your budget and schedule. Document all milestones and partial inspections in writing, and for larger projects, agree on contractual penalties for delays (§ 339 BGB)-a maximum of 5% of the contract amount is standard and legally sound.
A conventionally built single-family home typically takes 12-18 months from excavation to move-in. Prefabricated homes with a wood-frame construction can be ready for occupancy in 6-10 months, as the wall elements are prefabricated in the factory and assembly on the construction site is significantly faster. The actual construction time depends on the size of the building, soil conditions, weather, and-particularly relevant at present-the availability of tradespeople. In the Nuremberg region, we are observing a trend toward longer construction times due to the persistently high level of construction activity; construction delays of 20-30% compared to the original schedule are not uncommon.
During the construction phase, the following insurance policies are recommended: Builder’s liability insurance (strongly recommended-protects against third-party claims resulting from construction site accidents or damage to neighboring properties), Construction work insurance (protects your own building from weather-related and vandalism damage), Fire insurance for the building shell (often included free of charge in home insurance) and accident insurance for construction helpers (for work you do yourself or neighborly assistance - mandatory registration with BG BAU). If you’re using external financing, some banks also require construction completion insurance or a completion guarantee.
Change requests are generally possible, but the later they come, the more expensive they become. Planning changes after construction begins usually require addenda to the construction contract and can significantly delay the schedule. We recommend agreeing to all change requests in writing and clarifying the costs in a binding manner before placing the order. As a rule of thumb: Changes before construction begins cost planning time; changes during the shell construction phase cost money; changes during interior finishing cost both. Structural changes (moving walls, enlarging openings) may also require a new or amended building permit-expect this to add several weeks to the schedule.
Back to the Real Estate Glossary.
Want to know your property's value?
Get a market valuation in 2 minutes - free and non-binding.
Important Disclaimer
The information, assessments, and legal notes in this real estate glossary serve solely as general orientation. Despite careful preparation, we assume no liability for the accuracy, completeness, or timeliness of the content. These contents do not replace individual legal or tax advice. We strongly recommend consulting a qualified attorney or tax advisor for specific matters.
Get a free, non-binding valuation - in person or online.
We're where your property is - across the entire metropolitan region
To guarantee maximum speed in valuation and marketing, we have fully digitized our processes. We advise you exclusively and personally by phone or video call. On-site appointments at your property of course still take place in person. Visits to our headquarters in Weißenburger Str. by prior appointment only.
Talk directly with an expert.
Call - 0911 / 88 18 73 80Send us your inquiry via WhatsApp.
WhatsApp messageWe'll get back to you within 24 hours.