Urban Land-Use Planning - Urban land-use planning is the primary tool municipalities use to guide urban development. It consists of two stages: the Land-Use Plan (preliminary urban land-use planning) and the Zoning Plan (binding urban land-use planning). Urban land-use planning determines where and how construction is permitted within a municipality and serves as the legal basis for issuing building permits pursuant to Sections 2-10 of the German Building Code (BauGB).
Urban land-use planning is divided into two sequential planning stages:
Land Use Plan (F-Plan): The land use plan outlines the intended urban development for the entire municipal area. It broadly indicates which areas are designated for residential, commercial, agricultural, transportation, or green space use. The land use plan is not directly legally binding on individual citizens, but it is binding on the municipality itself when drawing up development plans. Zoning plans must be developed from the land use plan (Section 8(2) of the German Building Code (BauGB)).
Zoning Plan (B-Plan): The zoning plan specifies the provisions of the land use plan for a sub-area of the municipality. It is legally binding and specifies in detail: Type of building use (building area type according to BauNVO), extent of building use (floor area ratio, floor space index, number of stories), buildable land areas (building lines, building boundaries), traffic areas, and green spaces. Building permits may only be issued if the project complies with the provisions of the B-Plan.
| Procedure Type | Legal Basis | When Applicable | Special Features |
|---|---|---|---|
| Standard Procedure | Sections 2-10 BauGB | New planning / major changes | Full environmental assessment required |
| Simplified Procedure | Section 13 BauGB | Changes to existing development plans | No new environmental assessment, reduced public participation |
| Expedited Procedure | § 13a BauGB | Infill development < 20,000 m² GRZ | No environmental impact assessment |
| Infill Development Zoning Plan | § 13b BauGB | Residential land on the outskirts | Simplified public participation, limited to 10,000 m² |
The drafting of a development plan follows a legally regulated procedure in accordance with §§ 2-10 BauGB:
For affected property owners, active participation in the public participation process is crucial: Those who do not raise objections during the ongoing process may lose the opportunity to successfully challenge the plan later in a judicial review proceeding. Legal representation during the public participation phase is worthwhile when significant economic interests are at stake.
The zoning plan contains numerous provisions that directly influence the value and developability of a property:
We recommend that property owners and prospective buyers in the Nuremberg metropolitan region review the applicable zoning plan before making any purchase or construction plans. The City of Nuremberg makes many zoning plans available online via the Geoportal Nürnberg (geoportal.nuernberg.de) - where zoning plans, land-use plans, and ongoing planning procedures can be accessed. Pay particular attention to ongoing plan amendment procedures - a planned rezoning of an adjacent area (e.g., from commercial to residential) can significantly affect the value of your property.
Take advantage of public participation processes to advocate for your interests as a property owner-especially if a planned infill development in your neighborhood would impair your sunlight, view, or peace and quiet. In Nuremberg’s growth districts such as Lichtenreuth (the former Südbahnhof site), Langwasser-Nord, or Gebersdorf, new zoning plan procedures are regularly underway that can have significant impacts on adjacent existing properties.
In so-called unplanned inner areas (§ 34 BauGB), a project is permitted if, in terms of the nature and extent of the building use, the construction method, and the buildable land area, it fits into the character of the immediate surroundings and the infrastructure is secured. In the outlying area (§ 35 BauGB), only privileged projects (e.g., agriculture, wind energy, utility facilities) are generally permitted. Without a zoning plan, the developer has less planning certainty, as the assessment is made on a case-by-case basis by the building authority and may vary from case to case. A preliminary building inquiry provides binding clarity in this regard.
Within one year of the zoning plan’s publication, an application for judicial review may be filed with the competent Bavarian Administrative Court (BayVGH) in Munich (Section 47 VwGO). A prerequisite is that the applicant’s rights are affected by the plan. Typical grounds for challenge include inadequate consideration under § 1(7) BauGB, a missing or flawed environmental assessment, procedural errors in public participation, or a violation of higher-level planning requirements. The success rate of such applications is limited, but in serious cases, it is the right course of action. We recommend seeking legal advice early on from an attorney specializing in administrative law.
Drawing up a zoning plan generally takes one to three years-depending on the complexity, the number of comments, and the need for political coordination. Under the expedited procedure pursuant to Section 13a of the German Building Code (BauGB) (development plans for infill development), the process can be shortened to 6-12 months, as the environmental assessment is waived. In the Nuremberg metropolitan region, development plan procedures often take longer than planned in practice, as staffing capacities at the city planning office and the relevant authorities are limited. Developers awaiting new planning approval should factor in generous time buffers in their financial planning.
Back to the Real Estate Glossary.
Want to know your property's value?
Get a market valuation in 2 minutes - free and non-binding.
Important Disclaimer
The information, assessments, and legal notes in this real estate glossary serve solely as general orientation. Despite careful preparation, we assume no liability for the accuracy, completeness, or timeliness of the content. These contents do not replace individual legal or tax advice. We strongly recommend consulting a qualified attorney or tax advisor for specific matters.
Get a free, non-binding valuation - in person or online.
We're where your property is - across the entire metropolitan region
To guarantee maximum speed in valuation and marketing, we have fully digitized our processes. We advise you exclusively and personally by phone or video call. On-site appointments at your property of course still take place in person. Visits to our headquarters in Weißenburger Str. by prior appointment only.
Talk directly with an expert.
Call - 0911 / 88 18 73 80Send us your inquiry via WhatsApp.
WhatsApp messageWe'll get back to you within 24 hours.