Skip to content

Building permit

Term from the field of Land & Development

Building Permit - A building permit is the formal administrative act issued by the competent building authority certifying that no public law regulations preclude a construction project. It grants the builder the right to carry out the approved project in accordance with the submitted construction plans and any conditions attached.

The building permit certifies the compliance with public law of a construction project. This means that the authority has reviewed and confirmed the project’s compliance with building planning law (BauGB, zoning plan), building regulations (BayBO), and other public law regulations. The permit is a favorable administrative act and provides the builder with legal certainty against subsequent objections.

In Bavaria, the validity period of the building permit is four years from the date it becomes final. Construction must begin within this period. If the deadline is missed, the permit expires and a new building application is required. Upon request, the validity period may be extended by two years at a time, provided that the factual and legal circumstances have not changed significantly. An extension should be requested well in advance of the deadline, as an expired permit can no longer be extended.

The building permit may be subject to conditions and ancillary provisions. Common conditions relate to fire safety measures, the provision of parking spaces, the design of the facade, or noise protection requirements. These conditions are binding-a violation may result in a prohibition on use or in subsequent orders. The building owner has the option to file an objection to onerous conditions without calling the entire permit into question.

Projects Exempt from Permits and Protection of Neighbors

Not every construction project requires a building permit. In Bavaria, Art. 57 BayBO governs projects exempt from permits. These include, among other things, buildings with a gross floor area of up to 75 m³ (unless located in an outlying area), garages and covered parking spaces with a floor area of up to 50 m², terrace roofing of up to 30 m², as well as certain fences and walls. The exemption from permit procedure under Art. 58 BayBO also allows construction to begin without a formal permit, provided the project falls within the scope of a qualified zoning plan and no deviations are required.

Neighbors have a protected legal status in the permitting process. They are involved in certain projects and may file objections within two weeks. If the authority grants the permit nonetheless, the neighbor may file an appeal and subsequently bring an action before the administrative court. Provisions relevant to neighbor law include, in particular, the setback regulations under Art. 6 BayBO, the right to preservation of the area, and the requirement to show due consideration under building planning law (§ 15 BauNVO).

Building Permit and Grandfathering

A granted and final building permit establishes grandfathering for the constructed building. This means: Even if building regulations change after completion, the existing building may continue to be used in its approved condition. However, this grandfather clause has limits-it expires in the event of fundamental changes in use, structural alterations that go beyond mere maintenance, or if the building stands vacant for a long period and ceases to serve its function. In practice, grandfathering plays a particularly important role for older buildings in downtown Nuremberg, where new zoning plans often impose stricter requirements regarding setbacks or the number of stories. Anyone purchasing an existing building should clarify whether any additions or roof extensions are also approved-unauthorized structures do not enjoy grandfathering.

Practical Tip for Nuremberg and Franconia

In Nuremberg, the city’s Building Authority (Bauordnungsamt) issues building permits (Bauhof 2, 90402 Nuremberg). We recommend informally informing neighbors about the project before submitting the application and obtaining their consent in writing-this significantly speeds up the process and avoids future legal disputes. Especially in the densely built-up neighborhoods of Nuremberg’s Südstadt, St. Johannis, or Gleißhammer, coordination with neighbors is a key factor for success. In the surrounding areas, the respective district office is responsible-such as the Nürnberger Land District Office in Lauf an der Pegnitz or the Fürth District Office in Zirndorf. We also recommend keeping an eye on the validity period of the building permit and applying for an extension in a timely manner if there are delays in the construction process-the extension fee is usually between 100 and 300 euros and is significantly cheaper than a new building application.

Frequently Asked Questions

What is the difference between a building application and a building permit?

The building permit application is the application submitted by the builder to the authorities - the building permit is the authorities’ response to this application. The building permit application includes all construction documents (floor plans, sections, elevations, building specifications, site plan) and is prepared and submitted by the architect authorized to submit construction documents. The processing time in Bavaria is legally capped at three months, but in practice, it is currently often longer with Nuremberg authorities. A preliminary building inquiry can help quickly clarify fundamental questions of admissibility without going through the full application process.

Can a building permit that has been granted be revoked?

Revocation is only possible under strict conditions-for example, if the permit was obtained through false information or if circumstances subsequently arise that pose a threat to public safety. A legally granted building permit enjoys grandfathering and cannot be revoked without good cause. However, the authority may revoke the permit if construction does not begin within the specified timeframe or if the builder fails to comply with a material condition on a permanent basis. If there is uncertainty regarding the validity of an older permit, we recommend consulting with the building authority.

How much does a building permit cost in Bavaria?

The fees are based on the construction costs of the project and are calculated according to the Cost Regulation of the Free State of Bavaria. For a typical single-family home, the permit fees amount to approximately 0.2 to 0.7 percent of the construction costs-for a new build with construction costs of 500,000 euros, this means between 1,000 and 3,500 euros. In addition, there are fees for deviations, special construction reports, and, if necessary, inspection by a certified expert. Compared to the total costs of a construction project, the permit fees are moderate, but should be factored into the ancillary costs from the outset.

Back to the Real Estate Glossary.

Want to know your property's value?

Get a market valuation in 2 minutes - free and non-binding.

Important Disclaimer

The information, assessments, and legal notes in this real estate glossary serve solely as general orientation. Despite careful preparation, we assume no liability for the accuracy, completeness, or timeliness of the content. These contents do not replace individual legal or tax advice. We strongly recommend consulting a qualified attorney or tax advisor for specific matters.

What is your property worth?

Get a free, non-binding valuation - in person or online.

We're where your property is - across the entire metropolitan region

Get in touch

To guarantee maximum speed in valuation and marketing, we have fully digitized our processes. We advise you exclusively and personally by phone or video call. On-site appointments at your property of course still take place in person. Visits to our headquarters in Weißenburger Str. by prior appointment only.

Write to us

We'll get back to you within 24 hours.